Prioritization Matrix2 min read

In a recent LinkedIn discussion, questions were asked about the short-comings of prioritization matrices. I would like to highlight the strengths and weaknesses of using such a tool for portfolio management. Firstly, a prioritization matrix differs from a more traditional scoring approach in that it offers a limited number of priority selections. The most simplistic prioritization matrix has three choices, low, medium, and high. Of course, to be effective, every choice should have some predefined criteria. Otherwise, the matrix is of little value because decision makers can have wildly different views for what is of high importance versus low importance.

Strengths
Prioritization matrices have three primary strengths: simplicity, speed, and applicability to all types of work. Prioritization matrices are easy to understand and simple to use. Calculations are not required for determining the relative priority of a project. Basic criteria should be developed for each part of the matrix, but once complete, decision makers can apply the criteria to various types of work. Because of its simplicity, prioritization becomes a much faster exercise and allows decision makers to quickly distinguish important projects from less important projects. In addition, various kinds of work can be prioritized using a prioritization matrix. With a traditional scoring model, it is difficult to evaluate “keep the lights on” type of work, but with a prioritization matrix it is easier to compare priorities for project and non-project work.

Weaknesses
Prioritization matrices are unable to produce a rank ordered list of projects in a portfolio. At best, such a matrix can provide a categorical ranking of projects in the portfolio, but this won’t help prioritize projects within the same category. Prioritization matrices cannot do a good job of evaluating projects based on multiple criteria, and therefore cannot do a thorough job of distinguishing important projects from less important projects. When evaluating multiple large projects, a scoring system will provide a more accurate analysis over a prioritization matrix.

When Should a Prioritization Matrix Be Used?
Prioritization matrices are good for organizations new to the portfolio management process. Due to the simplicity, organizations can quickly get the benefit of prioritization without spending the time to do a thorough scoring of each project. Even in organizations where projects are scored and ranked, prioritization matrices can be used for “pre-screening” purposes to do a preliminary prioritization. This would be commonly used in a stage-gate process before a formal business case has been developed. A governance team could quickly determine a categorical priority for the project at an early gate review. Prioritization matrices can also be used to triage large volumes of project requests to focus the organization on the hottest projects. I have seen this approach used in an organization that received a high volume of small project requests. In this case, scoring would be an overkill; the organization just needed to determine the most important work at that time.

This was a guest article written by Tim Washington from Point B.

SHARE THIS POST

LinkedIn
Twitter
Facebook

Related Blog​s

Greater Value From Portfolio Management Systems

Enterprise repository (“single source of truth”)—having a single system that contains up-to-date and accurate project and portfolio data is valuable. Gone are the days of maintaining multiple versions of static Excel files that contain the current “authorized” list of projects. This value is magnified easier to access the system and the greater

Read More »
Application Portfolio Management

Key Metrics for Application Portfolio Management (APM)

Application Portfolio Management (APM) is a framework for managing applications in enterprise. APM provides an inventory of an organization’s software applications and software-based services as well as metrics showing the business benefits of each application.Metrics can provide information from various perspective such as business ,

Read More »

How to Prioritize Project Features and Explain the Process to the Stakeholders

When the Requirements Specifications is complete, the project manager (or the business analyst) must inspect the document with all the stakeholders in order to (along with other very important things) prioritize all of the project features and/or requirements. Project features have to be prioritized for the following reasons:Prioritization eliminates unnecessary, frivolous scope items added

Read More »
Join our email list to stay up to date on relevant and informative industry insights
Lead Source

Cloudbyz is focused on building innovative enterprise applications and solutions natively on cloud to help enterprises to be innovative and agile.

© Cloudbyz 2020. All Right Reserved.